1BETA 1450/ 850 MOBILE ALUMINIUM TOWERASSEMBLY GUIDEMay 2007www.turner-access.co.ukInstruction Manual EN 1298-IM-ENThese instructions and the equipmen
1010The Quantity Schedule provides for double handrails to all platforms. Toeboards have been included to one working platform only therefore addition
11The tower must be checked on a daily basis and after any signicant weather changes e.g. high winds, snow, frost.Use the checklist below prior to us
1212Whilst our recommended method of assembly to fully comply with the Work at Height Regulations 2005, is by using Advanced Guardrails (PlusGard™), a
13 Assembly Procedure 1450 Tower - 3TStabilisersWhen specied, the correct stabilisers or outriggers must always be used. See Quantity Schedule.Whe
1414 Assembly Procedure 1450 Tower - 3TAttach two diagonal braces from lower frame to upper frame in accordance with bracing pattern.Attach one more
15Fit two legs and castors (or base plates) to one 4 rung span frame (see illustration) and two legs and castors to one 4 rung ladder frame. Turn the
1616Odd Height TowersAttach two diagonal braces to the bottom rung of each base frame, with one brace being placed so the brace hook is as far to the
17 Assembly Procedure 1450 Tower - 3TPlace xed platform initially at 3m level and slide across to opposite side of tower (as shown) from where ope
1818 Assembly Procedure 1450 Tower - 3TDescend to platform level below and remove top platformRemove diagonal brace xed to upper frames.Remove uppe
2020BETA TowerFor Technical advice (or further information) on BETA Towers, please contact:Turner Access Ltd, 65 Craigton Road, Glasgow, G51 3EQTel: +
3 BETA 1450/850 GuideIntroductionPlease read this guide carefully.The BETA tower is a Load Class 3 tower as specified in BS EN 1004:2004.This instruc
44 ComponentsAdjustable LegCastorEnd ToeboardsToeboards2 Rung Span Frame2 Rung Ladder Frame4 Rung Span Frame4 Rung Ladder FramePlatform (Fixed and T
5General Safety NotesEnsure that all necessary components and safety equipment are available and operational.Inspect the tower components for signs of
66Mobile access towers are not designed to allow them to be lifted or suspended.PlusGard™ is personal protection equipment only and should not be used
7 Quantity Schedule - 1450 3T MethodBETA 1450 Ladderspan Tower - 1.8m and 2.5m (complies with BS EN 1004:2004)Internal/ External Use Internal Use o
88The Quantity Schedule provides for double handrails to all platforms. Toeboards have been included to one working platform only therefore additional
9 Quantity Schedule - 850 3T MethodBETA 850 Ladderspan Tower - 1.8m and 2.5m (complies with BS EN 1004:2004)Internal/ External Use Internal Use onl